On Sheldon Avenue, the new Lagana Park has started to look finished. The Village's October updates reported the plantings, sidewalks and courts installed, and by its November 6 update the sod was down. Next came the fence and the playground equipment, which was scheduled to start installing the following week. One piece will still be missing after the gates open. In its November 6 Tarrytown Link, the Village put off painting the courts until spring "to allow for the courts to settle."
So the park is coming back in stages, and the order makes sense. The playground and pavilion are expected around the start of December, and the court lines come once the ground has had a winter. The construction itself has been quick. The slow part came before any digging, when the Village had to prove which part of 171 Sheldon Avenue officially counted as park.
The Grant Came Before the Map
Lagana Park's renovation began as a state grant. The Village of Tarrytown won $500,000 from the New York State Office of Parks, Recreation and Historic Preservation's Environmental Protection Fund. The state announced the award on November 15, 2023, and the Village got formal notice on December 27, 2023. The Board of Trustees accepted it on February 6, 2024, according to that meeting's minutes. The Village's budget calls it a 50/50 matching grant.
Then came a step most people never saw. The grant money could only be spent on official parkland. The January 6, 2025 Board minutes explain that improvements paid for by the grant "may not include land that is not parkland." Lagana Park became parkland in October 1971. That designation left out the former Pennybridge School building, which the Elizabeth Mascia Child Care Center leases from the Village long-term. Nobody had drawn an exact line between the two, so the Village paid for one.
Why a School Building Shaped the Map
Insite Engineering surveyed the site in a map dated August 28, 2024, and the state parks office accepted it that same month. The Board adopted it on January 6, 2025, as the official map of Lagana's parkland. That parkland covers the fields, courts, picnic area and playground areas. It excludes the former Pennybridge School building plus a ten-foot buffer around it, running out to the street along Sheldon Avenue.
The ten-foot line explains the park's layout. Everything the grant pays for sits inside it, and the child care center's building stays outside it. The survey set where the new park could go before anyone sketched a playground.
Design started after that. The Village held a public meeting on March 31, 2025, and used what it heard there along with survey responses collected before the grant application. PS&S Design Consultants presented the first concepts, which covered playgrounds, courts, fields, paths, trees and shade. On October 6, 2025, the Board saw a detailed plan. That month, The Hudson Independent reported the park was scheduled to open early in 2026. The bid process pushed that date back.
Eleven Bids, One Yonkers Contractor
The Village advertised the construction bid on April 29, 2026, and opened eleven sealed bids at Village Hall on June 4. The bids were far apart:
| Bidder | Bid |
|---|---|
| Tony Casale, Inc. | $1,689,000.00 |
| ZN | $1,745,214.70 |
| Spitale | $1,790,763.25 |
| Dubner | $2,835,457.05 |
The winning bid came in about $56,000 under the next one. The highest bid was more than $1.1 million above it. Village staff and PS&S, the consulting engineer, recommended Tony Casale, Inc. of Yonkers as the lowest responsible bidder. The Board awarded the contract on June 15, 2026, by a 7–0 vote. According to the resolution, the project is funded partly by the state grant and partly by new borrowing. Against a $1,689,000 contract, the $500,000 grant covers roughly 30 percent of construction.
The resolution lists the work as site grading, landscaping, fencing, walking paths, a playground, a pavilion, and basketball, tennis and pickleball courts. The June 15 minutes state the purpose as giving residents "safe and high-quality recreational facilities" while also helping the Village meet its climate resilience goals.
The Order the Park Is Coming Back In
Work started two months after the award. The Village's newsletter, The Tarrytown Link, has tracked each step:
- August 24: The contractor started grading and removing the old playground.
- October 9: Plantings and sidewalks were in, and court work was set to start the next week. The Village expected most of the work done by October 19, apart from playground equipment, which was held up by lead times.
- October 23: The courts were in. Sod, court painting and fencing were next, and the playground equipment and pavilion were expected at the "end of November, early December."
- November 6: The sod was down, the fence was next, playground installation was due to begin the following week, and court painting had moved to spring.
Between the October 23 and November 6 updates, court painting moved from the next-up list to spring. The pieces that needed the most lead time, the playground equipment and the pavilion, became the last ones to arrive this year. The newest pieces of pavement will spend the winter settling before anyone paints lines on them.
What the Plan Puts on the Playground
The October 2025 plan the Board reviewed splits the playground into two areas, one for ages 2 to 5 and one for ages 5 to 12. The plan shows this equipment:
- an embankment slide built into the slope
- a universal carousel
- a seesaw and swings
- a music panel
- a fire-truck play structure
- a Starsurfer and a Sway Alley
- a sensory-dome net climber
The universal carousel and the sensory pieces are the accessibility features in the design. The same plan shows an entrance path, existing and new trees for screening, and the picnic pavilion. The pavilion and picnic tables were already part of the state grant's description of the project. The pavilion was also in the June 2026 construction scope and is one of the last items on the current schedule. The Lagana Park Improvements page holds the Village's project materials for anyone who wants to compare the plan with what goes in.
Courts That Wait for Spring
The courts will matter most for Tarrytown's tennis and pickleball players, and they're the part that has to wait. The grant called for upgrading Lagana's tennis courts so they work for both tennis and pickleball, next to the existing basketball court. The October 2025 plan draws separate basketball, tennis and pickleball courts.
Today, the Village's Parks and Recreation page lists Pierson Park on West Main Street as its tennis site, with hard-surface courts. Patriots Park appears there as a playground and basketball site, and Losee Park is listed for Basher Field's two ballfields. By April 2024, the Pierson courts were open to pickleball as well. Court time there has been booked through CourtReserve, and the Village's CourtReserve page lists an email contact for questions.
Once Lagana's courts are painted in the spring, the village will have a second public site for tennis and pickleball, up on Sheldon Avenue just south of the Thruway. Families with a junior player in the Village's 2026 Fall Jr. Tennis Program, which runs age groups for 4 to 9 and 10 to 16, can keep an eye on whether future sessions use Lagana's courts.
The Village's latest forecast puts the playground equipment and pavilion at the end of November or early December, and the court painting in the spring.
A renovated park a few blocks away is the kind of local detail that belongs in an accurate picture of your home's value. If you live near Sheldon Avenue and want to know how your street compares in today's market, Anthony Lando can walk you through the numbers. Request a Free Home Valuation and we'll start with the blocks around Lagana Park.